 | 12 November 2007 The I19 front end is installed. |  | 9 July 2007 Now that the steelwork has been erected the room partitions are put in place. |
 | 6 July 2007 The cabin roof sections have been added and the hand rails have also been completed. |  | 26 June 2007 The final steelwork sections are in place and the ladder is added. |
 | 26 June 2007 The cabin steelwork day 2. |  | 25 June 2007 The cabin steelwork grows. |
 | 25 June 2007 The cabin steel work starts to go up. |  | 20 June 2007 The steel work has arrived for the cabins and the floor area has been cleared. |
 | 20 June 2007 The cable trays are added. |  | 29 May 2007 Additional unistrut is added and the carriers for the cable trays are mounted. |
 | 8 May 2007 Cabins and services work begins with the uprights for the hand rails installed. |  | 30 March 2007 The hutches are now complete. |
 | 26 March 2007 The top coat of paint has now been applied on the hutches for I19. |  | 23 March 2007 The hutches are now constructed and the primer paint is now applied. |
 | 23 March 2007 The final roof panel is lowered into place to complete the construction of the hutches. |  | 22 March 2007 The walls have been completed and the painting process has started. The optics hutch is partially painted in a pastel yellow primer. |
 | 13 March 2007 The optics hutch and experimental hutch EH1 are now complete while the door sections for experimental hutch EH2 are next to be put in place. |  | 13 March 2007 The walls of the optics hutch are complete and the walls of experimental hutch EH1 are almost finished too. EH2 is taking shape also. |
 | 6 March 2007 The back wall of the experimental hutches. |  | 6 March 2007 Doors being attached to the optics hutch and experimental hutch 1. |
 | 28 February 2007 Floor elements of experimental hutch 1. |  | 28 February 2007 The optics hutch walls are almost complete. |
 | 16 February 2007 The components are placed on the optics hutch floor which will provide an x-ray seal for the base of the wall panels. |  | 16 February 2007 With the optics hutch floor elements and rachet wall elements in place the installation of the wall panels begins. |
 | 16 February 2007 Components arrive for constructing the optics hutches. |  | January 2007 The floor area where the I19 hutches will be built. |
 | January 2007 The experimental area allocated to I19, prior to construction of the hutches | | |