Beamlines | I12 - Construction photos

10 March 2010        The second crystal through the viewport    
10 March 2010        Only a few centimeters to go 10 March 2010          A first look into the monochromator through the viewport
10 March 2010        The monochromator lid is lowered into OH2 10 March 2010      The whole team helping to put the lid in position
19 February 2010    Small detector table 1 in its final position in EH1

 

15 March 2010       EH1 after installation of the final components with anti-scatter guard and PSS fencing
19 February 2010    Large detector table 1 part assembled in EH1 19 February 2010    View into EH1 through the open roof from the synchotron walk way

 

19 February 2010 Preparation for installation of large detector tables onto the base

 

19 February 2010   Module 4 of the large detector table is lowered into EH1
15 February 2010 Survey of large detector table base plate into its final position

 

17 February 2010      Base plate for large detector table grouted into place

 

12 February 2010    Large detector table 1 base plate was lowered into EH1

 

12 February 2010    Large detector table 1 base plate was lowered into EH1

 

9 February 2010 Monochromator crystals with cable managment installed

 

9 February 2010 Monochromator crystal 2 with bracket for cable managment

 

14 January 2010 Installation of small detector table base plate in EH1

 

 

9 February 2010 Monochromator crystals with cable managment
  18 December 2009 Cabeling of monochromator finished

 

18 December 2009 Cabeling of monochromator finished

 

11 December 2009

Testing of camera modules by PDRA Robert Atwood and support scientist Christina Reinhard

11 December 2009

Testing of camera modules

7 December 2009

Installation of large sample table in Experimental Hutch 2

   
  11 December 2009

Installation of large sample table in Experimental Hutch 2

11 December 2009

Installation of large sample table in Experimental Hutch 2

  7 December 2009

Installation of large sample table in Experimental Hutch 2

8 December 2009

Installation of large sample table in Experimental Hutch 2

  3 December 2009

Building of the camera modules

3 December 2009

Building of the camera modules

3 December 2009

Building of the camera modules

3 December 2009

Building of the camera modules

3 December 2009

Flat panel detector in the support laboratory

3 December 2009

Flat panel detector in the support laboratory

27 November 2009

First user group from Oxford University and principal beamline scientist Michael Drakopoulos (left)

27 November 2009

First user group and support scientist Christina Reinhard (left)

27 November 2009

Additional lead shielding for EDXD detector

27 November 2009

Samples for first user experiment

20 November 2009

Setup for EDXD first user experiment in Experimental Hutch 1 (with temporary tables)

 
20 November 2009

Setup for EDXD first user experiment in Experimental Hutch 1 (with temporary tables)

 
18 November 2009

Setup for EDXD first user experiment in Experimental Hutch 1 (with temporary tables)

18 November 2009

EDXD rack with shielding in Experimental Hutch 1

18 November 2009

Experimental Hutch 1 entry window installed with alignment laser

18 November 2009

Experimental Hutch 1 entry window with alignment laser

18 November 2009

Lower Huber sample stage installed and commissioned

18 November 2009

Lower Huber sample stage installed and commissioned

18 November 2009

Cabins & Services in Optics Hutch 3 finished

18 November 2009

Cabins & Services in external building finished

  2 October 2009

White beam stop vessel in Optics Hutch 2 in position

  2 October 2009

Shutter and pump stand in Experimental Hutch 2

  2 October 2009

Installation of the Huber sample stage base plate

  2 October 2009

Installation of the Huber sample stage base plate

  22 September 2009

Testing of the monochromator motion along the beam axis

  22 September 2009

Testing of the monochromator motion along the beam axis

  18 September 2009

External building

  18 September 2009

External building

  22 August 2009

Mechanical assembly of monochromator second crystal carriage

  23 August 2009

Delivery of lower Huber stage for Experimental Hutch 1

  18 August 2009

Control Room 1

 

 

22 August 2009

Mechanical work on monochromator ongoing

 

 

30 July 2009

Factory acceptance test for Huber sample stage

 

 

18 August 2009

Installation of secondary slits in Optics Hutch 2

 

 

30 July 2009

Factory acceptance test for Huber sample stage

 

  30 July 2009

 

Factory acceptance test for Huber sample stage

 

  3 July 2009

 

Continuous work on the monochromator mechanics

 

  3 July 2009

 

Installation of the large detector table base frame in Experimantal Hutch 2

 

  22 May 2009

 

Installation of copper filters in Optics Hutch 2

 

 

22 May 2009

Installation of copper filters in Optics Hutch 2

First light on I12

12 May 2009

First Light. Pictures of fluorescence from CVD diamond filter in Optics Hutch 1.

I12 first light

12 May 2009

First Light. Pictures of fluorescence from CVD diamond filter in Optics Hutch 1.

12 May 2009

Beam on for Optics Hutch 1

   

12 May 2009

I12 team in the Control Room for first light

12 May 2009

Controls Engineer Ulrik Pedersen setting up for first light

7 May 2009

Optics hutch 3 from the inside

7 May 2009

Walls for Data Analysis Room and Control Room 2 in the external building

9 April 2009

External building with lead hutches installed

7 May 2009

Building works going on in Experimental Hutch 2

9 April 2009

Optics Hutch 3 lead walls

9 April 2009

External building with lead hutches installed

26 March 2009

Installation of components in Optics Hutch complete

09 April 2009

Lead walls for Experimental Hutch 2 finished

17 March 2009

I12 wiggler in its final position in the storage ring

26 March 2009

Installation of components in Optics Hutch 1 completed (collimator, diamond windows)

16 March 2009

Installation of I12 wiggler into the storage ring

16 March 2009

Installation of I12 wiggler into the storage ring

3 March 2009

View upstream through hall for beam pipe in Optics Hutch 3

16 March 2009

Installation of I12 wiggler into the storage ring

 

3 March 2009

Construction of lead hutches in external building

 

3 March 2009

Construction of lead hutches in external building

 

9 February 2009

Beam for monochromator

9 February 2009

Beam for monochromator

12 January 2009

Connectors of 23 element horseshoe detector

9 February 2009

Assembly of monochromator crystal cage

12 January 2009

Crystals of 23 element horseshoe detector

12 January 2009

23 element horseshoe detector in detector lab during first setup

8 January 2009

Craneworks in external building

8 January 2009

Craneworks in external building

8 January 2009

External building

 

8 January 2009

Floor layout of Experimental Hutch 2 in external building

 

2 December 2008
Monochromator chamber with Design Engineer Adrian Birt (left) and Senior Mechanical Engineer Tim Hill (right).

 

2 December 2008

Monochromator chamber.

 

7 November 2008

General view of External Building site

 

7 November 2008

External building roofing in progress

  7 November 2008

External building roofing in progress

  28 October 2008

Steelwork being completed

  28 October 2008

Crane back on site to install the remaining steelwork

  28 October 2008

Experimental Hutch 2 roof complete

  22 October 2008

Control Cabin 1

 

22 October 2008

Experimental Hutch 1

  22 October 2008

Optics Hutch 1

 

17 October 2008

Forest of scaffolding for the roof shuttering work

 

17 October 2008

Experimental Hutch 2 roof cast

 

17 October 2008

External Building site

 

29 September 2008

Side view of building and Experimental Hutch 2

 

29 September 2008

Experimental Hutch 2 walls complete

 

29 September 2008

General view of External Building site

 

9 September 2008


Internal beamline, installation of wall and roof panels of control room and instrumentation areas.

 

9 September 2008
Internal beamline, installation of wall and roof panels of control room and instrumentation areas.

 

9 September 2008
The size of the EH2 bunker is apparent in this view.

 

9 September 2008
External building general site view. Bunker wall reinforcement still growing.

 

22 August 2008
External Building view from west side.

 

22 August 2008
External Building bunker reinforcement and shuttering.

 

22 August 2008
External Building general site view.

 

22 August 2008
Alignment of front end begins.

 

22 August 2008
View through the opening in the storage ring roof, with the I12 front end installed.

 

19 August 2008
Port shutter and absorber next to I12's port in the storage ring wall.

 

19 August 2008
Storage ring roof off and first parts of front end in.

 Steel framework of control & instrumentation areas either side of OH1-OH2 beamtube

15 August 2008
Steel framework of control & instrumentation areas either side of OH1-OH2 beamtube

 

15 August 2008
Inside EH1.

 

15 August 2008
Removing the storage ring tunnel roof.

 

12 August 2008
External Building bunker wall and floor slab reinforcement.

 

15 August 2008
External Building bunker wall reinforcement started.

 

6 August 2008
I12 Front End assembled on the main experimental hall floor for vacuum baking and testing.

 

6 August 2008
I12 Front End assembled on the main experimental hall floor for vacuum baking and testing.

 

6 August 2008
First section of transport pipe between the internal and external parts of the beamline.

 

6 August 2008 
First section of transport pipe between the internal and external parts of the beamline.

 

6 August 2008
External Building concrete work below ground level nearing completion.

 

2 July 2008
Concrete pumping for sample stage pit floor.

 

2 July 2008
Concrete pumping for sample stage pit floor.

 

26 June 2008

Sample stage pit zone being prepared for first concrete pour.

 

26 June 2008

"Inside" the External Building.

 

 

19 June 2008

Additional piling and excavation of pit zone for sample stages.

 

13 June 2008

I12 External Building site. Steel frame continues to grow.

 

13 June 2008

I12 External Building. End view. More steelwork waiting to be added.

 

6 June 2008

Steel building frame takes shape.

 

6 June 2008

Steelwork continues.

 

6 June 2008

I12 External Building site.

 

4 June 2008

First steelwork for External Building being erected - view from lab 69.

 

4 June 2008

The first steelwork for the External Building is erected. 

 

23 May 2008

View of I12 External Building Site. Piling completed and building shell foundations poured.

 

23 May 2008

Part of External Building shell foundations.

 

7 May 2008

Piling in progress.

 

7 May 2008

Piling Machine on I12 external building site. The depth of the piles is about 3/4 of the length of the drill string.

 

8 April 2008

View of I12 External Building construction site.

 

8 April 2008

Drainage diversion and ground preparation for I12 External Building.

 

25 March 2008

Removing cladding from main building

 

5 March 2008

I12 groundbreaking ceremony for JEEP beamline

 

February 2008

Internal Transfer Tube Installation

 

February 2008

I12 Internal Transfer Tube Work in Progress

 

7 December 2007

Interior of Experimental Hutch 1.  

 

7 December 2007

I12 Hutch Construction. Internal hutches painted

 

28 November 2007

I12 Hutch construction. OH1 and Side Station hutches being painted.

 

22 November 2007

I12 Hutch Construction. Roof panel of EH1 being installed

 

9 November 2007

End view of Experimental Hutch 1 from the walkway. 

 

9 November 2007

View through the beam tube hole at the end of Experimental Hutch 1. The transfer pipe to the External Building will start here. 

 

9 November 2007

View from the Storage Ring roof. Optics Hutch 1 is in the foreground. 

 

7 November 2007

Working on the tricky corner where Experimental Hutch 1 meets the walkway. 

 

5 November 2007

Downstream wall of Experimental Hutch 1 being installed. 

 

5 November 2007

"South" side of beamline, with Optics Hutch 2 walls compete and Expermental Hutch 1 in progress. 

 

31 October 2007

Using one of Diamond's 20 tonne cranes to lift a wall panel for Experimental Hutch 1. 

 

31 October 2007

Experimental Hutch 1 in progress. 

 

26 October 2007

Installing upstream wall of Experimental Hutch 1. 

 

26 October 2007

First panels for Experimental Hutch 1 being installed. 

 

23 October 2007

Downstream wall of Optics Hutch 2 complete. 

 

17 October 2007

Optics Hutch 2, awaiting end wall installation. 

 

14 October 2007

Optics Hutch 2 in progress.

 

9 October 2007

Upstream wall of Optics Hutch 2 in place. 

 

5 October 2007

Optics Hutch 1 and Side Station construction continues. 

  5 October 2007

 

The first panels of Optics Hutch 1 are being installed by the rachet wall.