Beamlines | I07 | Construction photos

That main constuction phase is now complete and the beamline is undergoing commissioning. These photos show the construction process as is happened.

Image of first light

May 2009

First Light
Read the news item

April 2009

Diffractometer installed in first experimental hutch

April 2009

Diffractometer Installation

March 2009

Large Area Detector Positioning system is installed in first experimental hutch

 

March 2009

Components installed in optics hutch

 

March 2009

Components installed in optics hutch

 

March 2009

Control room furniture is installed

 

March 2009

Internal view of mirrors after installation

 

February 2009

KB Mirrors lifted into optics hutch

 

February 2009

KB Mirrors in place in the optics hutch

 

February 2009

Double Crystal Monochromator lifted into optics hutch

 

February 2009

Internal view of Double Crystal Monochromator

 hutch goes up

9 December 2008

Services nearing completion

 hutch goes up

12 November 2008

Handrails fitted

 hutch goes up

28 October 2008

Pipework being installed

 hutch goes up

28 October 2008

Beamline components

 hutch goes up

22 September 2008

Beamline components assembled on the hall floor pre-installation

hutch goes up 

22 September 2008

View along the beamline

 hutch goes up

2 September 2008

The control cabin takes shape

 hutch goes up

2 September 2008

Steelwork for the control and instrumentation area (CIA)

 I07 hutch

24 October 2007

The I07 hutches are complete.

 I07 hutch

24 October 2007

The I07 hutches.

 I07 hutch

24 October 2007

The experimental hutch

 I07 hutch

24 October 2007

The I07 hutches.

 

16 August 2007

The two experimental hutches.

 Last panels going into place

16 August 2007

The last panels are lifted into place.

 Both hutches

16 August 2007

The second experimental hutch (EH2) is almost complete.

 EH1 complete

13 August 2007

The first experimental hutch is complete.

 EH1  

9 August 2007 

Construction continues on EH1.

 EH1 going up

9 August 2007

The first Experimental Hutch (EH1) under construction.

 Optics hutch almost complete

30 July 2007

Construction of the Optics hutch is almost complete.

 Hutch fixings

12 July 2007

The fixings for the hutches are attached to the ratchet wall in preparation.

Construction begins 

11 July 2007

Construction begins.

I07 before start 

17 May 2007

The area of the experimental hall where I07 will be built is cleared.